ARNCLIFFE STREET, WOLLI CREEK

Wolli Creek Traffic Improvements and Stormwater Upgrades

Bayside Council is working to improve traffic flow and safety for road users, pedestrians and cyclists in Wolli Creek. In November 2018, Council presented residents with two different options for a one-way system. Over 50% supported the option to make Arncliffe Street, Guess Avenue, Mt Olympus Boulevarde and Magdalene Terrace a one-way circuit.

Bayside Council has now engaged Sydney Civil to implement the chosen one way circuit and other improvements. These will include increased street lighting, widening and beautification of footpaths and roads, extra pedestrian crossings, adding a bicycle lane and addressing storm water issues to fix localized flooding.

Work is scheduled to commence early in the New Year. It will start with the permanent introduction of the one-way circuit. This will support traffic flow when work begins on the stormwater upgrades and other improvements.

The details of the work to be undertaken are as follows:

Location: Arncliffe Street, Willis Street, Guess Street, Mount Olympus Boulevarde and Magdalene Terrace.

Duration: Approximately one year (weather permitting)

Commencement: Mid/Late-January 2020

One way: to be set up from 28 January 2020 (to remain permanently)

Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, and business and car users. Please follow the directions of traffic controllers at all times.

Some construction activities can involve noise and vibration. Some of the main sources of noise during construction include excavators and trucks. Sydney Civil is committed to minimising the impact of our works on the surrounding community.

Feedback and Questions

If you have any questions, please complete the online form.

Project Updates

If you wish to be informed of project updates and other projects nearby, please register.

March 2020

Progress works for March: We have completed the channel stormwater system, kerb and gutter, and driveway reconstruction on the west side of Willis Street

February 2020

Our work started in early February. Some minor delays were experienced due to the severe weather earlier this month, and a complex intersection of electrical, water and gas services with the new drainage system. However, a solution was quickly identified and our key milestones have been achieved:

Works on Willis Street, Wolli Creek

  • Location: Willis Street
  • Scope: Improvement to surface drainage and road reconstruction
  • Duration: Approximately two months (weather permitting)
  • Working Hours: Mon-Fri: 7:30 to 17:00 and Sat: 8:00 to 15:00
  • Commencement: 3 February 2020

Parking: There will be parking loss on both sides of Willis Street for the duration of the works.

 

Works on Arncliffe Street, Wolli Creek

  • Location: Works are to commence outside No 50 to No 76 Arncliffe Street.
  • Scope: Drainage Improvements
  • Working Hours: Mon-Fri: 7:30 to 17:00 and Sat: 8:00 to 15:00
  • Commencement: 13 February 2020

 

  • Submit your Q&A or Feedback

    If you have any questions about this project, please complete this form.

    Take this Survey

Concept Plan