ARNCLIFFE STREET, WOLLI CREEK

Wolli Creek Traffic Improvements and Stormwater Upgrades

Bayside Council is working to improve traffic flow and safety for road users, pedestrians and cyclists in Wolli Creek. In November 2018, Council presented residents with two different options for a one-way system. Over 50% supported the option to make Arncliffe Street, Guess Avenue, Mt Olympus Boulevarde and Magdalene Terrace a one-way circuit.

Bayside Council has now engaged Sydney Civil to implement the chosen one way circuit and other improvements. These will include increased street lighting, widening and beautification of footpaths and roads, extra pedestrian crossings, adding a bicycle lane and addressing storm water issues to fix localized flooding.

Work is scheduled to commence early in the New Year. It will start with the permanent introduction of the one-way circuit. This will support traffic flow when work begins on the stormwater upgrades and other improvements.

The details of the work to be undertaken are as follows:

Location: Arncliffe Street, Willis Street, Guess Street, Mount Olympus Boulevarde and Magdalene Terrace.

Duration: Approximately one year (weather permitting)

Commencement: Mid/Late-January 2020

One way: to be set up from 28 January 2020 (to remain permanently)

Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, and business and car users. Please follow the directions of traffic controllers at all times.

Some construction activities can involve noise and vibration. Some of the main sources of noise during construction include excavators and trucks. Sydney Civil is committed to minimising the impact of our works on the surrounding community.

Feedback and Questions

If you have any questions, please complete the online form.

Project Updates

If you wish to be informed of project updates and other projects nearby, please register.

October 2020

Progress works for October: 90% road line marking and signs completion. Final asphalt reconstruction. Progress of electrical works.

September 2020

Progress works for September: Completed road reconstruction on Guess Av. Completed road reconstruction on Mount Olympus Blv. Completed road reconstruction works on Arncliffe Street. Completed garden beds and tree pits along Arncliffe St.

August 2020

Progress works for August: Continue road reconstruction on Guess Av. Continue road reconstruction on Mount Olympus Blv. Completed installation of cycleway median separator on Mount Olympus Blv. Completed concrete island at Magdalene Tce. Continue pedestrian crossing update works on Magdalene Tce and Mount Olympus Blv.

July 2020

Progress works for July: Continue road reconstruction on Guess Avenue. Continue road reconstruction on Mount Olympus. Continue electrical upgrade works along Arncliffe Street.

June 2020

Progress works for June: Complete drainage works on Guess Avenue. Continue road reconstruction on Guess Avenue. Continue storm water upgrade, kerb and gutter and footpath reconstruction on Arncliffe Street (North Side).

May 2020

Progress works for May: commence road reconstruction on the North side of Arncliffe Street, commence footpath upgrade along Guess Avenue, commence storm water works on Guess Avenue, commence footpath upgrade on Mount Olympus Blvd.

April 2020

Progress works for April: completed the channel stormwater system, kerb and gutter, and driveway reconstruction on the East side of Willis Street.

March 2020

Progress works for March: We have completed the channel stormwater system, kerb and gutter, and driveway reconstruction on the west side of Willis Street

February 2020

Our work started in early February. Some minor delays were experienced due to the severe weather earlier this month, and a complex intersection of electrical, water and gas services with the new drainage system. However, a solution was quickly identified and our key milestones have been achieved:

Night works 

  • Scope of works: Minor line marking works
  • Location: Arncliffe Street, Guess Avenue, Mount Olympus and Madaglene Terrace
  • Working Hours: 8pm to 6am
  • Working Dates: 15th of October

Night works 

  • Scope of works: Asphalt and line marking works
  • Location: Arncliffe Street and Guess Avenue
  • Working Hours: 7pm to 5am
  • Working Dates: 1st and 2nd and 3rd of October

Night works 

  • Scope of works: Road Re-sheeting
  • Location: Arncliffe Street, Guess Avenue, Mount Olympus
  • Working Hours: 7pm to 5am
  • Working Dates: 6th and 7th of September

Night works 

  • Location: Guess Avenue and Mount Olympus Boulevarde
  • Scope: Roadworks upgrade
  • Working hours: 10th 11th and 12th of August from 8pm to 5am

 

Works on Guess Avenue, Wolli Creek

  • Location: Guess Avenue (from under the rail bridge to Mount Olympus Boulevarde).
  • Scope: Guess Avenue roadworks upgrade
  • Working Hours: Mon-Fri: 7:30 to 17:00 and Sat: 8:00 to 15:00
  • Commencement: 22 June 2020

Please note that changed traffic conditions will be in place for the duration of construction works as one travelling lane will be closed at a time. A set of temporary traffic lights will be installed to allow vehicular movement in both directions.  Please follow all signs and directions given by traffic controllers at all times.

 

Works on Willis Street, Wolli Creek

  • Location: Willis Street
  • Scope: Improvement to surface drainage and road reconstruction
  • Working Hours: Mon-Fri: 7:30 to 17:00 and Sat: 8:00 to 15:00
  • Commencement: 3 February 2020

Parking: There will be parking loss on both sides of Willis Street for the duration of the works.

 

Works on Arncliffe Street, Wolli Creek

  • Location: Works are to commence outside No 50 to No 76 Arncliffe Street.
  • Scope: Drainage Improvements
  • Working Hours: Mon-Fri: 7:30 to 17:00 and Sat: 8:00 to 15:00
  • Commencement: 13 February 2020

 

 

 

 

 

 

No Survey Found.

Concept Plan