    Progress works for April:

    • Completed the channel stormwater system, kerb and gutter, and driveway reconstruction on the East side of Willis Street.
    • Completed road reconstruction on Willis Street.
    • Commenced grated drain channel construction on the Northern side of Arncliffe St.
    • Commenced storm water works on Guess Avenue.
    • Commenced grated drain channel on Arncliffe St, West of Willis St (Northern side).

     Program of works for May:

    • Continue drainage works on Guess Avenue.
    • Continue storm water upgrade, kerb and gutter and footpath reconstruction on Arncliffe Street (North side).
    • Commence road reconstruction on the North side of Arncliffe St.
    • Commence road reconstruction on Guess Avenue. 

     