ARNCLIFFE STREET, WOLLI CREEK

Project Updates

  • August 2020

    Progress works for August:

    • Continue road reconstruction on Guess Av.
    • Continue road reconstruction on Mount Olympus Blv.
    • Completed installation of cycleway median separator on Mount Olympus Blv.
    • Completed concrete island at Magdalene Tce
    • Continue pedestrian crossing update works on Magdalene Tce and Mount Olympus Blv.

     Program of works for September:

    • Complete road reconstruction works on Guess Av.
    • Complete road reconstruction works on Arncliffe Street.
    • Final asphalt for the above (see note on night works as notified previously).
    • Complete garden beds and tree pits along Arncliffe St.
    • Final road line marking and signs.

    Night works

    • Road Re-sheeting night work is scheduled on the 6th and 7th of September from 7pm to 5am at Arncliffe Street, Guess Avenue, Mount Olympus.