ARNCLIFFE STREET, WOLLI CREEK

Project Updates

  • February 2020

    Our work started in early February. Some minor delays were experienced due to the severe weather earlier this month, and a complex intersection of electrical, water and gas services with the new drainage system. However, a solution was quickly identified and our key milestones have been achieved:

    Completed for the month:

    • Works on Willis Street, including the first half of a deep excavation for road reconstruction, and the beginning of a channel stormwater system
    • Works on Arncliffe Street including trenching for the storm water upgrade

     

    Programmed for March:

    • Continuing work on the Willis Street stormwater upgrade, and the second half of the deep excavation for the road reconstruction
    • Continuing work on the storm water upgrade on Arncliffe Street.

     

    Please note the new one way system is now in operation and it is a permanent traffic arrangement. Follow all signs and directions given by traffic controllers.