October 2020
Progress works for October:
- 90% road line marking and signs completion.
- Final asphalt reconstruction.
- Progress of electrical works.
Program of works for November:
- Complete footpath line marking.
- Complete works at Willis Street.
- Complete electrical works.
- Works completion.
Please note the new one way system is now in operation and it is a permanent traffic arrangement. Please follow all signs and directions given by traffic controllers.
Category :
Project Update
Created On :
29 October 2020