ARNCLIFFE TOWN CENTRE

Project Updates

  • November/December 2020

    Progress works for November:

    • Complete kerb and footpath works adjacent to bus stop and taxi rank.
    • Complete footpath works on the West side of Arncliffe Road (between Wollongong Rd and Done Street).
    • Finalise landscaping works on the Wollongong Road side (pocket park).
    • Complete kerb works on the West side of Firth Street between Belmore Street to Done Street.
    • Complete all works on the Eastern side of Firth Street (only works remaining are outside train station).

    Program of works for December:

    • Complete paving and new tree pit work on the West side of Firth Street (between Belmore Street to Done Street and Forest Road to Queen Street).
    • Complete driveway works South of Queen Street on Firth Street.
    • Secure site for the break period.