ARNCLIFFE TOWN CENTRE

Project Updates

  • September 2020

    Progress works for September:

    • Site establishment and preliminary works.
    • Demolish kerb and gutter and footpath for our two construction areas.
    • Form and pour concrete kerbs and dish drains
    • Prepare base for footpath construction on the Wollongong Rd end.

    Program of works for October:

    • Prepare base for footpath areas on the Forest Rd end.
    • Form and pour concrete footpath on both ends.
    • Form and pour concrete kerb for parking bays on the Forest Rd end.
    • Construct parking bays on the Forest Rd end.