Street improvements

Street improvements at Challis Avenue between Macleay Street and Victoria Street to renew the centre median island kerb and garden bed.

What work is being done?

• New concrete kerb

• Replant median garden bed

• Signage

• Asphalt roadway restoration

Please refer to the concept plan below.

The estimated construction period is January 2020 to March 2020.

Work will be carried out during the day between 7:30am and 5:30pm, Monday to Friday, and 7:30am and 3:30pm on Saturdays.

We will take steps to minimise any impacts on local residents and business owners. However, there will be some machinery noise, temporary parking restrictions and alternative access for people walking.

Feedback and Questions

If you have any questions, please complete the online form.

Project Updates

If you wish to be informed of project updates and other projects nearby, please register.

  • Submit your Q&A or Feedback

    If you have any questions about this project, please complete this form.

    Take this Survey

Concept Plan