Construction update 26.05.25

24 May 2025

Day works:

  • Between Arthur Street to Davies Street – continue with footpath paving, kerb and gutter work, stormwater work and electrical work
  • Between Jesson Street and Davies Street – Stormwater trenching
  • Intersection of Albion Street and Crown Street - continue electrical work for light pole installation
  • Intersection of Foveaux Street and Crown Street – continue electrical work for light pole installation
  • Between Arthur Street and Collins Street – service location to prepare for works starting on 2 June

Night work

  • Outside Crown Street Public school – TCS work
  • Intersection of Foveaux Street and Crown Street – TCS work