Construction works continue at Crown Street between Foveaux Street to Albion Street (west), between Foveaux Street to Collins Street (alongside Shannon Reserve) and at the intersection of Little Oxford Street and Goulburn Street.

Our construction work for the week commencing 05 August weather permitting includes:

  • From Foveaux Street to Albion Street - continue footpath, kerb and gutter works between 359 to 351 Crown Street.
  • Intersection of Crown Street at Little Oxford Street and Goulburn Street - continue electrical work and footing for new lighting poles.
  • Foveaux Street to Collins Street (alongside Shannon Reserve) - continue paving works.

We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

Your patience and cooperation during this period are much appreciated.

Please get in touch with the Community Liaison team with any questions or concerns.