Construction update for week commencing 10 February 2025

8 February 2025

Dear stakeholder,

Construction works will continue at Crown Street between Jesson Street to Arthur Street.

Our construction work for the week commencing 10 February weather permitting includes:

  • Between Jesson Street to Arthur Street. - kerb and gutter work, drainage work and bus shelter footing.

We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

Your patience and cooperation during this period are much appreciated.

Please get in touch with the Community Liaison team with any questions or concerns.