Construction works will continue at Crown Street, please see below our program of work.

Our construction work for the week commencing 10 June weather permitting includes:

Day works:

  • Intersection of Foveaux Street and Crown Street - kerb and gutter work
  • Between 500 Crown Street to Davies Street - porous paving installation and tactiles installation
  • Intersection of Albion Street - continue electrical work
  • Outside Crown Street Public School - electrical work
  • Between Collins Street and Arthur Street - road closure set up at the intersection of Collins and Crown Streets for up to 4 weeks. Electrical work and excavation work.

Night works:

  • Intersection of Foveaux Street - excavation and concrete work
  • Between 500 Crown Street to Davies Street - clean and seal of pavers

We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

Your patience and cooperation during this period are much appreciated.

Please get in touch with the Community Liaison team with any questions or concerns.

Thank you,

Crown Street Upgrade project team