News

Construction update for week commencing 12 August 2024

9 August 2024

Dear stakeholder,

Construction works continue at Crown Street between Foveaux Street to Albion Street (west) and at the intersection of Little Oxford Street and Goulburn Street.

Our construction work for the week commencing 12 August weather permitting includes:

  • From Foveaux Street to Albion Street - continue paving, kerb and gutter works between 359 to 351 Crown Street and electrical work at the intersection of Crown Street.
  • Intersection of Crown Street at Little Oxford Street - footpath, kerb works and continue footing for new lighting poles.

We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

Your patience and cooperation during this period are much appreciated.

Please get in touch with the Community Liaison team with any questions or concerns.

Thank you,

Crown Street Upgrade project team