News

Construction update for week commencing 12 May 2025

10 May 2025

Dear stakeholder,

Construction works will continue at Crown Street, please see below our program of work.

Our construction work for the week commencing 12 May 2025 weather permitting includes:

Day works:

  • Between Arthur Street to Davies Street - continue with footpath paving, kerb and gutter work, stormwater work and electrical work
  • Road Closure at Davies Street starting Monday 12 May - saw cutting, footpath excavation and concrete pour
  • Intersection of Albion Street and Crown Street - continue electrical work for light pole installation
  • Intersection of Foveaux Street - continue electrical work for light pole installation

Night works:

  • Intersection of Foveaux Street - continue TCS work

We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.