Construction Update for week commencing 18 November 2024

15 November 2024

Dear stakeholder,

Construction works continue at the intersection of Litte Oxford Street, intersection of Goulburn Street and between Rainford Street and Davies Street.

Our construction work for the week commencing 18 November weather permitting includes:

  • Intersection Little Oxford Street - construction of new continuous footpath treatment.
  • Intersection of Goulburn Street - private electrical connections.
  • Between Rainford Street to Davies Street - continue electrical work for underground services and private connections.

Clean and seal of pavers will continue along different sections of Crown Street. Work will take place from Sunday to Thursday, between 8:00 PM and 5:00 AM.

We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

Your patience and cooperation during this period are much appreciated.

Please get in touch with the Community Liaison team with any questions or concerns.

Thank you,

Crown Street Upgrade project team