Construction update for week commencing 19 May 2025

17 May 2025

Dear stakeholder,

Construction works will continue at Crown Street, please see below our program of work.

Our construction work for the week commencing 19 May 2025 weather permitting includes:

Day works:

  • Between Arthur Street to Davies Street – continue with footpath paving, kerb and gutter work, stormwater work and electrical work
  • Intersection of Albion Street and Crown Street - continue electrical work for light pole installation
  • Intersection of Foveaux Street and Crown Street – continue electrical work for light pole installation

Night works

  • Corner of Arthur Street and Crown Street – Ausgrid work
  • Crown Street between Clifton Reserve and Reservoir Street – TCS work
  • Intersection of Foveaux Steet and Crown Street – TCS work

Please note: Ausgrid power outage planned for Wednesday 21 May 8pm to 5am

We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.