Dear stakeholder,

Construction works continue at Crown Street between Foveaux Street to Albion Street (west), at the intersection of Little Oxford Street and Goulburn Street and at the intersection of Jesmond Street.

Our construction work for the week commencing 26 August weather permitting includes:

  • From Foveaux Street to Albion Street - complete electrical work.
  • Intersection of Crown Street at Little Oxford Street - continue kerb, gutter and footpath work.
  • Intersection of Crown Street at Goulburn Street - site set up and start electrical work.
  • Intersection of Crown Street at Jesmond Street - continue drainage works.

Access to Jesmond Street will be maintained during our works.

Road closure at the intersection of Crown Street and Goulburn Street will be in place for up to 6 weeks.

We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

Your patience and cooperation during this period are much appreciated.

Please get in touch with the Community Liaison team with any questions or concerns.