Construction works will continue at Crown Street, please see below our program of work.

Our construction work for the week commencing 28 April weather permitting includes:

Day works:

  • Intersection of Foveaux Street and Crown Street - continue electrical work for light pole installation
  • Between 500 Crown Street to Davies Street - continue footpath, kerb and gutter work and electrical work
  • 365 Crown Street - footpath reinstatement work

Night works:

  • Intersections of Foveaux Street and intersection of Albion Street - continue TCS work.

We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

Your patience and cooperation during this period are much appreciated.

Please get in touch with the Community Liaison team with any questions or concerns.

Thank you,

Crown Street Upgrade project team