News

Construction update for week commencing 28 January 2025

24 January 2025

Dear stakeholder,

Construction works will continue at Crown Street between Jesson Street to Arthur Street.

Our construction work for the week commencing 28 January weather permitting includes:

  • Between Jesson Street to Arthur Street. - footpath excavation, concrete work and drainage work.

Temporary Relocation of Bus Stop

The bus stop will be temporarily relocated to the section between Devonshire Street and Jesson Street for up to 10 weeks while construction is underway.

We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

Your patience and cooperation during this period are much appreciated.

Please get in touch with the Community Liaison team with any questions or concerns.

Thank you,

Crown Street Upgrade project team