Construction update for week commencing 31 March 2025

29 March 2025

Dear stakeholder,

Construction works will continue at Crown Street, please see below our program of work.

Our construction work for the week commencing 31 March weather permitting includes:

Day works:

  • Intersection of Foveaux Street and Crown Street - continue electrical work for light pole installation
  • Intersection of Albion Street and Crown Street - continue electrical work for light pole installation
  • Intersection of Arthur Street - continuous footpath treatment work. Road closure set up, please follow detour route.
  • Between 500 Crown Street to Davies Street - saw cut of footpath and roadway

Night works:

  • Intersections of Foveaux Street and intersection of Albion Street - continue TCS work.
  • Between Jesson Street to Arthur Street - clean and seal of pavers

We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

Your patience and cooperation during this period are much appreciated.

Please get in touch with the Community Liaison team with any questions or concerns.

Thank you,

Crown Street Upgrade project team