Construction update - Week commencing 7 July 2024

5 July 2024

Dear stakeholder,

Construction works continue at Crown Street between Albion Street to Campbell Street (west), between Foveaux Street to Fitzroy Street (west) and between Foveaux Street to Collins Street (alongside Shannon Reserve).

Our construction work for the week commencing 08 July 2024 weather permitting includes:

  • From Albion Street to Campbell Street (outside 285A Crown Street) – garden bed and paving works.
  • From Foveaux Street to Fitzroy Street - footpath and driveway renewal works.
  • Foveaux Street to Collins Street (alongside Shannon Reserve) - footpath and paving works.

Visit project website (link)

We will work to minimise impacts during this time, however there will be some machinery noise, temporary restrictions to parking and temporary changes to pedestrian access.

Traffic control will be available on site for the duration of works to assist pedestrians, cyclists, businesses and car users. Customers will be able to access businesses during our works. Please follow the directions of traffic controllers at all times.

Your patience and cooperation during this period are much appreciated.

Please get in touch with the Community Liaison team with any questions or concerns.

Thank you,

Crown Street Upgrade project team