George Street South Pedestrianisation

Project Updates

  • Stage 2C: Goulburn Street to Hay Street

    1. Pedestrianisation works now underway from Goulburn Street to Hay Street, on the West side.

    2. Works include demolition of existing road surface, removal of kerb and gutter, drainage, paving and street furniture installation.

    3. Construction is scheduled to be completed within 10-12 weeks.

    4. Work will predominantly be carried out during the day between 7:00am and 5:00pm (Monday to Saturday). Night works may be required.

    5. We make every effort to minimise impacts during construction, however there may be machinery noise, changes to pedestrian access and weather delays.