George Street South Pedestrianisation

Project Updates

  • Stage 5: Ultimo Road

    1. Pedestrianisation works will be commencing in Ultimo Road between George Street and Thomas Street, and Thomas Street at the intersection of Hay Street on Monday 21 March 2022.

    2. Works include widening of footpaths, new planting areas and installation of street furniture.

    3. Construction of this stage is scheduled to be completed within 15 weeks.

    4. Work will predominantly be carried out during the day between 7:00am and 5:00pm (Monday to Saturday). Night works may be required.

    5. We make every effort to minimise impacts during construction, however there may be machinery noise, changes to pedestrian access and weather delays.