Green Square town centre

Street Improvements

Street improvements at the northern section of Portman Street, Merton Street, and Hansard Street, between Joynton and Dunning avenues, Green Square town centre.These works will balance the demand for on-street parking while increasing safety for people walking and riding in the town centre..

What work is being done?

  • new raised intersection of Portman Street and Merton Street
  • new raised pedestrian crossing and lighting at Hansard Street and Joynton Avenue
  • new continuous footpath treatments and garden beds
  • new stormwater pits and pipes
  • new footpath lighting in Portman Street
  • new concrete footpaths, paving, road resurfacing and line marking

The estimated construction period is November 2022 to April 2023.

Work will be carried out during the day between 7:30am and 5:30pm Monday to Friday, 7:30am and 3:30pm Saturday.

We will take steps to minimise any impact on you, however there will be some machinery noise, temporary restrictions to vehicle parking and alternative pedestrian access.

You will still be able to access properties in the street, and we will contact you if we need to temporarily restrict access to progress work.

In the event of wet weather, work will commence the following day. If unsuitable weather continues, we will notify you of the change in scheduling.

Project Updates

If you wish to be informed of project updates and other projects nearby, please register.

  • Submit your Q&A or Feedback

    If you have any questions about this project, please complete this form.