Intersection of Lachlan Street and Gadigal Avenue, Zetland

Installation of traffic signals

Street improvements at the Intersection of Lachlan Street and Gadigal Avenue, Zetland.

What work is being done?

• Installation of traffic signals.

The estimated construction period is July 2020 to April 2021.

Work will be carried out during the day between 7:30am and 5:30pm, Monday to Friday, and 7:30am and 3:30pm on Saturdays.

We will take steps to minimise any impacts on local residents and business owners. However, there will be some machinery noise, temporary parking restrictions and alternative access for people walking.

Feedback and Questions

If you have any questions, please complete the online form.

Project Updates

If you wish to be informed of project updates and other projects nearby, please register.

February/March 2021

Works completed to date: Kerb and gutter, access ramps, garden beds, cycleway, footpath renewal and paving, street lighting, installation of traffic signals, new bench seating

January 2021

Works Completed: traffic signal equipment installation

December 2020

Works Completed To Date: Road, Kerb and Gutter, Access Ramps and Cycleway on the northern and southern side of intersection.

November 2020

Works Completed To Date: Road, Kerb and Gutter, Garden Beds, Access Ramps and Cycleway on the northern side of intersection

October 2020

Works Completed To Date: Construct kerb and cycleway (North-East corner). Re-construct road sections (North-East corner) along Gadigal Avenue and Lachlan Street. Re-construct footpath base for pavers (North-East corner). Site establish South-East corner. Demolish footpath and kerb (South-East corner).

September 2020

Works Completed To Date: Construction of new garden beds on the North- West corner; Complete road section along the North West corner; Establish work site on the North-East corner; Commence demolition and road works on the North-East corner; Prepare base for new road and cycle way on the North-East corner.

August 2020

Works Completed To Date: Pour concrete new kerb and gutter along Lachlan Street; Reconstruct road section along Gadigal Avenue and Lachlan Street; Installed poles footing and conduits for new traffic signal poles

July 2020

Works Completed To Date: Work site fenced off along Lachlan Street and Gadigal Avenue; Demolition of the existing road, kerb and gutter ; Pour concrete new kerb and gutter along Gadigal Avenue.

  • Submit your Q&A or Feedback

    If you have any questions about this project, please complete this form.

    Take this Survey

Concept Plan