Works completed to date: Kerb and gutter, access ramps, garden beds, cycleway, footpath renewal and paving, street lighting, installation of traffic signals, new bench seating
Works Completed: traffic signal equipment installation
Works Completed To Date: Road, Kerb and Gutter, Access Ramps and Cycleway on the northern and southern side of intersection.
Works Completed To Date: Road, Kerb and Gutter, Garden Beds, Access Ramps and Cycleway on the northern side of intersection
Works Completed To Date: Construct kerb and cycleway (North-East corner). Re-construct road sections (North-East corner) along Gadigal Avenue and Lachlan Street. Re-construct footpath base for pavers (North-East corner). Site establish South-East corner. Demolish footpath and kerb (South-East corner).
Works Completed To Date: Construction of new garden beds on the North- West corner; Complete road section along the North West corner; Establish work site on the North-East corner; Commence demolition and road works on the North-East corner; Prepare base for new road and cycle way on the North-East corner.
Works Completed To Date: Pour concrete new kerb and gutter along Lachlan Street; Reconstruct road section along Gadigal Avenue and Lachlan Street; Installed poles footing and conduits for new traffic signal poles
Works Completed To Date: Work site fenced off along Lachlan Street and Gadigal Avenue; Demolition of the existing road, kerb and gutter ; Pour concrete new kerb and gutter along Gadigal Avenue.