    Works Completed To Date

    • Pour concrete new kerb and gutter along Lachlan Street
    • Reconstruct road section along Gadigal Avenue and Lachlan Street
    • Installed poles footing and conduits for new traffic signal poles

    Current and Upcoming Works

    • Construction of new garden beds
    • Upgrade of footpath along Lachlan Street
    • Complete road section along the North West corner
    • Decommission worksite on the North West corner
    • Establish work site on the North East corner
    • Commence demolition and road works on the North-East corner

    Working hours:

    Day works: Mondays to Friday 7:30am to 5:30pm, Saturday 7.30am to 3.30pm

    Night works:  Some night works will be required and you will be notified in advance. See below for current night works scheduling

    Important Notes

    Night works:

    Traffic signal works across Lachlan St (7, 8 September 2020)

    Reinstate road after trenching has been completed across Lachlan St (28, 29 and 30 September 2020)

    Noisy works will be up to 10:30pm and sound barriers will be used to minimise the impact.