Intersection of Lachlan Street and Gadigal Avenue, Zetland

Project Updates

  • February/March 2021

    Works completed to date:

    • Kerb and Gutter

    • Access Ramps

    • Garden Beds

    • Cycleway

    • Footpath Renewal and Paving

    • Street Lighting

    • Installation of Traffic Signals

    • New Bench Seating

    Works Remaining:

    • Intersection Road Renewal and LineMarking

    • Garden and Tree Planting

    • Traffic Signals Switch-on

    Night Works:

    Road Renewal: 7pm to 5am - Wednesday 10 March and Thursday 11 March 2021 - Note that we will complete noisier works before 11.30pm wherever possible.

    Due to weather conditions road renewal work has been rescheduled for Monday 15 March 2021.

    Line Marking: 7pm to 5am –Tuesday 16 March and Wednesday 17 March 2021 –Note these are not noisy construction works