Intersection of Lachlan Street and Gadigal Avenue, Zetland

Project Updates

  • October 2020

    Works Completed To Date


    • Construct kerb and cycleway (North-East corner).
    • Re-construct road sections (North-East corner) along Gadigal Avenue and Lachlan Street.
    • Re-construct footpath base for pavers (North-East corner).
    • Site establish South-East corner.
    • Demolish footpath and kerb (South-East corner).


    Current and Upcoming Works


    • Prepare base and form and pour new kerbs for cycle way (South-East corner).
    • Form and pour concrete base for footpath (South-East corner).
    • Construct cycle way (South-East corner).
    • Site establish South-West corner.
    • Construct new pram ramps (South-West) corner.


    Working hours:


    • Day works: Monday to Friday 7:30am to 5:30pm, Saturday 7.30am to 3.30pm.
    • Night works: Night works are required for the completion of these works. Please refer below for current programmed schedule.


    Important Notes
    • Upcoming scheduled night works (9.30pm to 5.00am)
    19 November 2020
    23 to 26 November 2020