Intersection of Lachlan Street and Gadigal Avenue, Zetland

Project Updates

  • September 2020

     

    Works Completed To Date

    • Construction of new garden beds on the North-West corner.

    • Complete road section along the North West corner.

    • Establish work site on the North-East corner.

    • Commence demolition and road works on the North-East corner.

    • Prepare base for new road and cycle way on the North-East corner.


    Current and Upcoming Works

    • Upgrade of footpath along Lachlan Street on the North-West corner (final layer).

    • Construct kerb and cycleway section on the North-East corner.

    • Re-construct road sections of the North-East. corner along Gadigal Avenue and Lachlan Street.

    • Re-construct footpath and turf areas on the North-East corner.

    Working hours:

    Day works: Mondays to Friday 7:30am to 5:30pm, Saturday 7.30am to 3.30pm

    Night works:  Some night works will be required and you will be notified in advance.