Macleay Street Upgrade

Weekly Project Updates

  • Week 1 April to 8 April 2022

    1. Finish footpath paving works cnr. Greenknowe Ave. (West) and start footpath works (EAST)

    2. Continue kerb extension works opposite Challis Avenue (east).

    4. Start footway continuation works across Manning St.

    5. Localised footpath paving works around pits

    Note: WORKS ARE WEATHER PERMITTING