Macleay Street Upgrade

Weekly Project Updates

  • Week 12 April to 17 April 2021

    1. Commence paving works from pedestrian crossing opposite Rockwall Crescent to opposite Manning Street (East side).

    2. Sawcut at Crick Avenue intersection on Monday only, to prepare for Continuous Footpath Treatment construction. Please note temporary half road closures will be in place during sawcut, with traffic control assistance and alternate pedestrian crossing arrangements available.

    3. Commence kerb stone and gutter works on southern side of Crick Avenue.