Macleay Street Upgrade

Weekly Project Updates

  • Week 13 September to 18 September

    1. Complete driveway paving works from Crick Ave to opposite Rockwall Crescent (east).

    2. Continue construction of Continuous Footpath Treatment at Hughes Street.
    Please note temporary road closure and local traffic diversions will be in place during works.

    3. Commence footpath paving works from Rockwall Crescent to Manning Street (west).

    4. Continue localised works at utility pits.