Macleay Street Upgrade

Weekly Project Updates

  • Week 14 March to 19 March 2022

    1. Complete paving for Continuous Footpath Treatment at McDonald Street (west side).
    Please note a temporary road closure will be in place with local traffic diversions available.

    2. Continue footpath paving and commence kerb extension works opposite Challis Avenue (east).

    3. Continue with electrical footings works and laying new kerb stone at Greenknowe Avenue and Challis Avenue intersections.

    4. Commence footpath paving works inside Manning Street (North Side)

    5. Commence works to upgrade driveway opposite McDonald Street (East)

    NB: WORKS ARE WEATHER PERMITTING