    1. Complete footpath paving on southern side of Orwell Street.

    2. Complete kerb, gutter and footpath paving opposite McDonald Street (East side).

    3. Complete drainage works, and commence excavation of footpath in preparation for paving, between Hughes Street and Manning Street (West side).

    4. Complete drainage, kerb and gutter works between Challis Avenue and Rockwall Crescent (West side).

    5. No works will be scheduled on Monday 14 June for the Queen’s Birthday Public Holiday.