Macleay Street Upgrade

Weekly Project Updates

  • Week 15 March to 20 March 2021

    1. Commence excavation of footpath in preparation for paving between Orwell Street and Hughes Street (West side)

    2. Commence paving works between Challis Avenue and Rockwall Crescent (East side).

    3. Continue pot holing for street light footing installation in localised areas.

    Some residents and businesses may have received a letter of notification for footpath repair works along Macleay Street.

    We have discussed this with The City and agreed that this will not be required at this time.

    We will continue to monitor this area to ensure public safety and will complete the permanent repair as part of the main paving works.