    1. Underground electrical trenching works between Fitzroy Gardens and Greenknowe Avenue ( East side )

    2. Street Lighting Footing installation between Challis Avenue and Crick Avenue ( East side )

    3. Removal of existing median island between Manning Street and Rockwall Crescent.