    1. Complete paving for Continuous Footpath Treatment at McDonald Street (west side).
    Please note a temporary road closure will be in place with local traffic diversions available.

    2. Commence works to upgrade driveway opposite McDonald Street (east).

    3. Continue footpath paving and commence kerb extension works opposite Challis Avenue (east).

    4. Continue with electrical footings works and laying new kerb stone at intersection of Greenknowe Avenue intersection.