Macleay Street Upgrade

Weekly Project Updates

  • Week 21 March to 26 March 2022

    1. Complete paving for Continuous Footpath Treatment at McDonald Street (west side).
    Please note a temporary road closure will be in place with local traffic diversions available.

    2. Continue kerb extension works opposite Challis Avenue (east).

    3. Complete electrical footings works and laying new kerb stone at Greenknowe Avenue and Challis Avenue intersections.

    4. Complete footpath paving works and continue curb extension works inside and corner of Manning (North Side)

    5. Complete works to upgrade driveway opposite McDonald Street (East) and

    6. Localised footpath paving works around pits

    Note: WORKS ARE WEATHER PERMITTING