  • Week 26 April to 30 April 2022

    1. Continue paving and continuous footpath treatment at Rockwall Crescent.

    2. Footpath paving works at Intersection of Greenknowe Avenue.

    3. Kerb extension works at intersection of Challis Avenue.

    4. Continuous footpath treatment across Manning Street.

    5. Localised footpath paving works around pits and street lighting poles.

    6. Installation of street lighting poles along Macleay Street.

    7. NIGHT WORKS NOTICE: Electrical works for traffic signals at intersection of Challis Avenue and Greenknowe Avenue. ( No Noise )