Macleay Street Upgrade

Weekly Project Updates

  • Week 27 September to 1 October 2021

    1. Continue construction of Continuous Footpath Treatment at Hughes Street.
    Please note temporary road closure and local traffic diversions will be in place during works.

    2. Continue drainage, footpath excavation and paving works from Rockwall Crescent to Manning Street (west).

    3. Commence footpath excavation and paving works in Rockwall Crescent (south side).

    4. Continue seat installation and localised works at utility pits.