Macleay Street Upgrade

Weekly Project Updates

  • Week 28 June to 3 July 2021

    1. Commence construction of Continuous Footpath Treatment at Orwell Street. Please note temporary road closure and local traffic diversions will be in place during works.

    2. Complete paving works opposite McDonald Street (East side).

    3. Complete kerb and gutter works at footpath extension on southern corner of Macleay Street and Manning Street.

    4. Commence footpath paving works between Challis Avenue and Rockwall Crescent (West side).

    The safety of our communities, residents and staff is our top priority. With the current Covid-19 lockdown in Sydney, it may become necessary to reschedule works at short notice.