Macleay Street Upgrade

Weekly Project Updates

  • Week 5 July to 10 July 2021

    1. Complete construction of Continuous Footpath Treatment at Orwell Street.
    A temporary road closure at Orwell Street will be in place during works, with local traffic diversions available.

    2. Complete footpath paving works between Challis Avenue and Rockwall Crescent (West side).

    3. Complete kerb, gutter, garden bed and footway extension works on southern corner of Macleay Street and Manning Street.

    4. Commence footpath paving works in Challis Avenue (southern side).
    A temporary half-road closure will be in place at Challis Avenue during works, with traffic control assistance and local traffic diversions available.

    The safety of our communities, residents and staff is our top priority. With the current Covid-19 lockdown in Sydney, it may become necessary to reschedule works at short notice.