Macleay Street Upgrade

Weekly Project Updates

  • Week 6 September to 11 September 2021

    1. Complete footpath and driveway paving works from Crick Ave to opposite Rockwall Crescent (east).

    2. Commence construction of Continuous Footpath Treatment at Hughes Street.
    Please note temporary road closure and local traffic diversions will be in place during works.

    3. Continue localised works at utility pits.