Macleay Street Upgrade

Weekly Project Updates

  • Week 7 February to 12 February

    1. Continue works for Continuous Footpath Treatment at Rockwall Crescent (west side).
    Please note a half road closure will be in place with traffic control assistance.

    2. Commence electrical trenching works in roadway, followed by footpath paving works, inside Rockwall Crescent (north side).

    3. Continue kerb, gutter, and footpath paving works inside Hughes Avenue (west side).
    Please note a temporary road closure will be in place during works with local traffic diversions available.

    4. Continue construction of Continuous Footpath Treatment at McDonald Street (west side).
    Please note a temporary road closure will be in place with local traffic diversions available.

    5. Continue potholing for smartpole footings at intersection of Greenknowe Avenue.

    6. Nightworks scheduled on Thursday 10 February for minor traffic signal works at Greenknowe Avenue intersection.