Macleay Street Upgrade

Weekly Project Updates

  • Week 7 June to 12 June 2021

    1. Complete footpath paving on northern side of Orwell Street.

    2. Complete footpath and driveway paving from Challis Avenue to McDonald Street (East side).

    3. Complete footpath paving from Crick Avenue to opposite Manning Street (East side).

    4. Commence drainage works at pits between Hughes Street and Manning Street (West side).

    3. Continue installation of new street furniture.