    1. Continue footpath paving works from Rockwall Crescent to Manning Street (west).

    2. Complete construction of Continuous Footpath Treatment at Hughes Street (west).
    Please note temporary road closure and local traffic diversions will be in place during works.

    3. Complete footpath paving works opposite Orwell Street (east)
    Please note alternative pedestrian crossing arrangements will be in place during works.

    4. Continue localised works at utility pits.