Parramatta Road and Derwent Street, Camperdown

Street Improvements

Street improvements at the Intersection of Parramatta Road and Derwent Street, Camperdown. These works will increase pedestrian, bike and public transport access while improving safety.

What work is being done?

  • upgrade of traffic signals
  • stormwater pit and pipes
  • footway renewal
  • access ramps
  • linemarking

The estimated construction period is February 2023 to March 2023.

These works will be carried out during the day between 7:30am and 5:30pm Monday to Friday, 7:30am and 3:30pm Saturday.

Night works will be required, notification will be provided to the community prior to the commencement of these works.

All work is expected to take two weeks to complete, weather permitting

We will take steps to minimise any impact on you, however there will be some machinery noise, temporary restrictions to vehicle parking and alternative pedestrian access.

You will still be able to access properties in the street, and we will contact you if we need to temporarily restrict access to progress work.

In the event of wet weather, work will commence the following day. If unsuitable weather continues, we will notify you of the change in scheduling.

Project Updates

If you wish to be informed of project updates and other projects nearby, please register.

  • Submit your Q&A or Feedback

    If you have any questions about this project, please complete this form.