Street improvements at Pitt Street between Rawson Place and Barlow Street, Haymarket.
What work is being done?
• kerb and gutter, footway paving, and road reconstruction.
The estimated construction period is November 2023 to December 2023
Work will be carried out during the night between 8pm to 5am Monday to Thursday and during the day between 7:30am to 5:30pm and 7:30am to 3:30pm on Saturdays and Sundays.
We will take steps to minimise any impacts on local residents and business owners. However, there will be some machinery noise, temporary parking restrictions and alternative access for people walking.
Project Updates
If you wish to be informed of project updates and other projects nearby, please register.