Pyrmont Bridge Road, Pyrmont

Street Improvements

Street improvements at Pyrmont Bridge Road, Pyrmont, between Pyrmont Street and Murray Street, and including the intersection of Edward Street. These works will increase pedestrian, bike and public transport access while improving safety and greening our streets.

What work is being done?

• New pedestrian crossing across Edward Street
• Footpath paving along Pyrmont Bridge Road
• Kerb and gutter
• Garden beds
• Access ramps
• Line-marking
• Street lighting for pedestrian crossing


The estimated construction period is February 2022 to July 2022.

Work will be carried out during the day between 7:30am to 5:30pm Monday to Friday, and 7:30am to 3:30pm Saturday.

We will take steps to minimise any impacts on local residents and business owners. However, there will be some machinery noise, temporary parking restrictions and alternative access for people walking.

Project Updates

If you wish to be informed of project updates and other projects nearby, please register.

  • Submit your Q&A or Feedback

    If you have any questions about this project, please complete this form.