Please see below more information on upcoming works:

George Street North Pedestrianisation

Street: George Street

Section: Intersection of Grosvenor Street

Type of work: Construction of access ramp, kerb and gutter.

Start date: 14 October

Duration: Two weeks

Working hours: 8:00pm to 5:00am - Monday to Thursday

_____________________________________________________________

Street: George Street

Section: Curtin Pl

Type of work: Clean and Seal of pavers

Start date: 14 October

Duration: Three nights

Working hours: 7:00pm to 5am

_____________________________________________________________

Street: George Street

Section: between Essex Street and Hunter Street (west side)

Type of work: Removal of light pole, asphalt work, removal of concrete

barriers and replace with water barriers, replace pit lids on track and clean

cobble edge.

Start date: 14 October

Duration: Three nights

Working hours: 7:00pm to 5:00am

What to expect during construction work

As the City of Sydney’s contractor, Sydney Civil will take steps to minimise potential impacts during construction works.

However, there will be machinery noise, temporary restrictions to vehicle parking/loading zones, temporary lane closures and temporary pedestrian detours. Please follow the direction of signage and traffic controllers.

We will also erect temporary fencing and install barriers to create a safe working area for our construction team and the community.

Access to all businesses (retail, cafes, offices and driveways) will remain open during the construction works.

In the event of wet weather, unexpected ground conditions or other delays, work will commence the following day. If a delay continues, we will notify of the change in scheduling.

Please pass on this important information to your local contacts and tenants.

Contact us

If you have any questions or would like more information, please contact our Community team:

Email: community@sydneycivil.com

Phone: 1300 997 858

To learn more about the George Street North project